Purchases and stock
What it's for
Purchases follows materials from the site's request to the purchase order, the goods that arrive, and the stock held on each site. Stock is valued at the weighted average rate, so material used is costed correctly against the project.
Before you start
- Requests and stock need the stock permission on the project (Store Keeper, Site Engineer); orders need the purchase permission (Purchase Manager).
- Add materials under Materials & stock → Materials list → Add material: Name, Category, Unit, GST %, Reorder at, Code, and the cost head.
Ask for materials
- Purchases → Ask for materials.
- Pick the Project, Needed by and Priority (Normal or Urgent).
- Add lines: Material, Qty, For (where it is needed). Press Send request.
Requests show under Material requests. Press Order on one to start a purchase order from it, or Close with Done (no more needed).
Issue a purchase order
- New order (or Order on a request).
- Enter the Vendor, Order date, Deliver by, Deliver to (site address) and the lines with quantity, rate and tax. The Order total updates as you type. Add Terms.
- Press Issue order. If an approval policy for Purchase order matches (for example amount at or above a limit), the order waits in Approvals first.
- Open the order and press PDF to send it to the vendor.
Record goods received
- Goods received (on the order, or on the Purchases page).
- Choose Against order or No order (direct purchase), the Received on date, Challan / DC no. and Vehicle no.
- For each line enter the quantity received and Rejected. You cannot receive more than is still to come on the order.
- Press Add to stock. The order becomes partly received or received.
An order that will not be completed can be closed with Close (no more to come). A goods received note can be cancelled with Cancel GRN; its stock is taken out again.
Use, move and count stock
- Use (Material used): project, material, date, quantity, Used for / where and cost head. It leaves stock at the average rate and is costed to the project.
- Move: sends stock to another site at the average rate.
- Count (Stock count / opening stock): enter the Counted quantity; the difference is corrected. The first count on a site is its opening stock. Rate (for stock found) values extra stock. Reorder at (this site) overrides the material's level for this site.
Screens
- Materials & stock → Stock: in stock, average rate and value per site; tick Low stock only to see what to reorder.
- Movements: every receipt, use, move and count.
- Purchases: tabs Material requests, Purchase orders (Open orders, Closed, Cancelled) and Goods received (billed or not billed).
What happens automatically
- Stock never goes below zero: a use or move larger than the stock is refused.
- When a use takes stock down to the reorder level, a low-stock alert is raised and the material shows under Low stock on the Site dashboard.
- Goods received can be turned into a vendor bill with From goods received.
Tips and common questions
- Can I receive extra? No. Raise a new order for the extra quantity.
- Rejected quantity is not added to stock and is not billed.
Related: Vendor bills and payments · Approvals